NILAMBE HYDRO POWER STATION

Generator View

  • Installed capacity
    1.6 MW X 2
  • Expected annual average
    energy 14 GWh
  • Commissioned in 1988
  • Main contractors
    • Civil – China Complan
    • Electromechanical – China Complan
    • Hydro mechanical – China Complan
  • Located 10 km south-west of Kandy
  • Reservoir
    • Catchment area : 64 km2
    • Usable water volume : 40000 m3
    • Maximum level : 596 m above MSL
    • Minimum level : 594 m above MSL
  • Headrace
    • Open canal
    • 2560 m length
  • Penstock
    • Steel circular, 1.2 m diameter, 278.6 m length
  • Tailrace
    • Maximum level : 210.92 m above MSL
  • Generator (Fujaian Nanping)
    • 2000 kVA, 0.8 PF, 6.3 kV, 184 A
    • 50 Hz, 32 poles, 1000 rev/min
    • Exciter : 58.5 V, 284 A
  • Turbine (Fujaian Nanping)
    • Horizontal Francis
    • Output : 1.69 MW @ 110 m effective head (Rated), 1.69 MW @ 113.3 m effective head (Maximum)
    • 1000 rev/min